News  »  Major road works on Pickmere Lane in February 2018



   Major road works on Pickmere Lane in February 2018    January 22, 2018

NOTICE OF WORKS – Tanyard Culvert, Pickmere Lane, Pickmere

I am writing to inform you that the scheme of works to Tanyard Culvert, Pickmere Lane, is due to begin shortly, the exact start date is still to be determined but this is currently expected to be the week commencing 19th February 2018.  Please find attached a location plan of the structure for your information.

The proposed works are essential to restore and maintain the long-term serviceability of the structure and will involve the replacement of the entire structure.

As mentioned above the works are expected to start on site the week commencing 19th February 2018 and will take approximately 6 weeks to complete.  A full road closure will be necessary for the majority of the works however temporary traffic lights will be used whenever possible.  A diversion route for traffic will be signed via Higher Wincham and the A556.  Pedestrian access through the works will be maintained at all times.

Your contact for the works will be either Ian McLauchlan of Cheshire East Highways, on 01260 371043 or Richard Parkin, of Jacobs UK Ltd, on 01642 334 591.  We would like to apologise for any disruption caused as a result of these essential work and thank you in advance for your patience.